The Tanchon Power Station Project: Progress Lagging

상세내역
게재일자 2020년 11월 25일
기관 38North
저자 PETER MAKOWSKY, 38 NORTH
키워드 #AIRBUS   # DIGITALGLOBE   # ENERGY   # HYDROPOWER   # KCTV   # MARTYN WILLIAMS   # MAXAR   # PETER MAKOWSKY   # POWER STATION   # SATELLITE IMAGERY   # TANCHON
원문 보기
상세내역
주요내용 Recent commercial satellite imagery indicates construction progress on the highly touted Tanchon Hydroelectric Power Station Project is lagging. Despite the emphasis on this project in 2017—both in Kim Jong Un’s New Year’s address and in a May Pyongyang Times article—the rapid pace of construction observed from 2017 through September 2019 was not matched from then through 2020. Of the three key projects located in the vicinity of Tanchon, only Power Station No. 5 has shown signs that it is nearing completion. Progress on Power Station No. 6 and the Sinhong Dam continued, but at a much-reduced pace.